Digital system implementation at overseas plants

What preparations are needed before commissioning digital systems at an overseas plant?

Applies toDigital-system implementation, handover and trial operation at overseas plants

Key points

GB/T 45988 covers personnel, equipment, data, processes and trials. Use it to define operators, maintenance responsibilities, data inputs and trial operation.

01

Roles and responsibility

Align roles, responsibilities and competence with workflows; assign equipment provision, maintenance and upgrades.

02

Equipment and data

Prepare equipment and technical conditions; address data accuracy, consistency, completeness, control and confidentiality.

03

Trial-operation preparation

After initial implementation, plan trials and operating controls to check that data, technology, processes and organization work together.

Key points for digital-system implementation

AreaPublished requirementClause
Personnel and rolesAlign staffing, responsibilities, authority and competence with business processes.6.3, 7.2, 7.3
Equipment and technologyAssign provision, maintenance and upgrade responsibilities; address availability, maintainability, reliability and safety.6.4, 7.4
DataSupport collection, sharing and use while addressing quality, control and confidentiality.6.5, 7.5
Trial operationPlan trials and operating controls, coordinate the four elements and monitor operation.7.6